"I can get one more full season of the Viewline before the operator asks me to close or inject a substantial amount of capital." Stephane de Baets said this to Snowmass Town Council on Nov. 9, as The Aspen Times reported. His company has proposed replacing the Viewline Resort, the Snowmass Conference Center and Wildwood Lodge with a Ritz-Carlton.
The largest projects now under discussion in Snowmass Village all sit at the Mall end of the village: the hotel redevelopment, a replacement for the gondola that links the Mall to Base Village, a long-planned transit center, an expanded Snowmass Center, and several workforce housing proposals. They are at very different stages. One has a construction month and an opening holiday. One is a sketch with a projected timeline that runs into 2031. The rest have no schedule at all.
For a buyer comparing a condo near the Mall with one at Base Village, that spread matters more than any single rendering. The useful question is which of these years you plan to own through.
The one project with dates: the Skittles gondola, 2027
The Sky Cab gondola, which locals call "Skittles," runs between Base Village and the Mall. The Town and Aspen Skiing Co. are splitting the cost of a replacement estimated at about $10 million. Council started design and property-acquisition work in February 2026, according to The Aspen Times.
An August 2026 update in the Aspen Daily News filled in the schedule. The current gondola would run through June and July 2027, construction would start in August 2027, and the new lift would open on Thanksgiving 2027. It is designed to carry 1,000 people per hour, up from 510 today, with new terminals at both ends. The Town is also planning other ways to get people between the base and the Mall while the gondola is closed.
We covered what this change means on the mountain in our post on what's new at Snowmass this winter. On the property calendar, the gondola is the first item on the Mall calendar, its closure falls in summer and fall 2027, and it is planned to reopen with nearly double the capacity before the 2027–28 ski season.
The project that would reshape the core: the Ritz-Carlton, 2028 to 2031
Elevated Snowmass LLC, led by de Baets, has proposed 167 hotel rooms, 61 fractional-ownership residences, up to 125 deed-restricted workforce housing units, a new conference center, retail space and a garage, all under the Ritz-Carlton brand. De Baets also owns the St. Regis in Aspen and Redstone Castle, and he bought the Snowmass property last year.
The July sketch plan, as The Aspen Times described it, adds detail a buyer will care about:
- Hotel rooms would be about 60% larger on average than today's.
- Parking on the property would go from 25 spaces to 252, below grade.
- A centralized delivery area would have cold and dry storage that Mall businesses could rent.
De Baets told council the current buildings are "probably past the acceptable lifespan and needs to be redeveloped."
The same presentation laid out the developer's projected path:
- Sketch plan review from June through December
- Preliminary plan submittal from December through March 2027
- Preliminary plan review from March through October 2027
- Final plan submittal from November 2027 through February 2028
- Final plan review from March through June 2028
- Groundbreaking in autumn 2028
- Opening in spring or summer 2031
As this goes up, the sketch plan is still under review. On Oct. 7 the Snowmass Planning Commission recommended that council let it move forward, and the commission discussed nearly 40 conditions, including other options for massing and scale, landscape design and delivery facilities. Council opened its own review on Nov. 9, and its public hearing was scheduled to resume Nov. 16. A staff memo set lodging, commercial space and the conference center for Dec. 7, workforce housing for Dec. 21, and a draft resolution for early January 2027.
The sketch plan describes a lodge building 77 feet tall and a workforce housing building of 48 feet. At the October meeting, The Aspen Times reported, Planning Commissioner Jim Gustafson called it "the most significant project that we've looked at in Snowmass in the last 20 some years." His fellow commissioner Brian Marshack added a reminder about where it stands: "This is a Sketch Plan. I mean, there's no plan. It's a sketch."
The projects with no calendar yet
Next to the hotel, the Snowmass Mall Transit Center would be a rebuilt hub for RFTA and Village Shuttle buses. People in town have discussed it for decades. A 1986 Aspen Times article mentions a "Daly Lane Alternation" meant to improve traffic and pedestrian flow around the Mall. A 2024 engineering study put a two-level design at $39.3 million. The Town took preliminary construction out of its proposed 2026 budget in October 2025, The Aspen Times reported. A September 2026 Aspen Times report said $9.3 million remained for design and planning, and council members were split over whether they had heard enough from the public to move ahead.
In that same report, Council Member Britta Gustafson called the transit center "one of those projects that's going to enable everything else that's coming down the pipe." In July, according to The Aspen Times, Council Member Tom Fridstein suggested the Ritz-Carlton developer could help the town build it as a public benefit. The hotel and the bus hub are discussed together often enough that a buyer should follow both.
Down Kearns Road, council approved Eastwood Snowmass Investors' redevelopment of Snowmass Center in January 2025. The plan enlarges the center's footprint by 24%, gives Clark's Market more space, doubles the post office, and adds indoor gathering space and a rooftop public area. The Aspen Times reported that the approval also cleared the way for the Town to buy more than three acres behind the center for $12.5 million, with room for up to 130 workforce homes. The developer's project page says the land sale to the Town is complete, the residential and commercial work will follow separate schedules, and the commercial redevelopment has no fixed timeline.
Housing makes up the rest of the list. The Town's Draw Site plan is now a single $75 million building with 66 units and underground parking. Council gave it preliminary approval on a 3-2 vote on Jan. 20, 2026, according to the Aspen Daily News. A separate private proposal from WestPac would put 42 units on Daly Lane on land owned by the Snowmass Community Foundation. It reached sketch-plan review in August 2026, and questions about its height and parking are still open.
What the calendar means for a condo near the Mall
The village core has one firm construction window, the gondola in late 2027. If the Ritz-Carlton stays on its projected path, a longer window would follow, from autumn 2028 to an opening in 2031. Every other project around the Mall could fall before, during or after that stretch. In The Aspen Times' October coverage, Planning Commissioner Gustafson's concern was a long construction period leaving a "hole" in the center of the village. Snowmass Sports manager Cameron Wenzel spoke at the same meeting and called the project "the beginning of a revolution in the upper mall." Both describe the same calendar. They are looking at opposite ends of it.
A buyer's holding period sets which part of that calendar they own through. Someone buying a ski condo near the Mall this winter with a ten-year horizon would own through the construction years and into whatever the finished project becomes. Someone planning to sell within about three years would likely sell into the middle of the approval process, with a buyer asking the same questions you are asking now.
Location within the Mall area matters too. Public comment at the Planning Commission and council hearings has come largely from owners near the site, and it has centered on views, traffic and the construction period. A unit's distance from the Viewline site, and which way its windows face, will matter differently over the next five years than it did over the last five.
The finished project would also bring a new kind of ownership to the Mall. The 61 fractional residences would be offered in two- through five-bedroom layouts and sold in one-eighth shares. In July, The Aspen Times reported, Council Member Britta Gustafson asked how that model would keep "hot beds" filled, and she asked for more detail at future meetings. A buyer weighing whole ownership of a Mall-area condo against a share in a branded residence nearby is making a choice about use and cost. The final design will shape that choice, so the comparison is worth revisiting as the preliminary plan comes in during 2027.
Base Village buyers face a different calendar. Their nearest dated change is the gondola connection, which is planned to reopen faster and with nearly twice the capacity in time for the 2027–28 season. For costs in that part of the village, see our breakdown of Base Village ownership costs, and for recent pricing, our read on Snowmass condo prices through August.
A few common questions
Is the Ritz-Carlton approved? No. As of this week, Town Council is reviewing the sketch plan, with sessions scheduled for Dec. 7 and Dec. 21 and a draft resolution expected in early January 2027. The developer's own timeline places groundbreaking in autumn 2028.
When would the Viewline close? The developer's July timeline puts groundbreaking in autumn 2028. In November, de Baets told council he expects "one more full season of the Viewline" before the operator asks him to close it or put in substantial capital.
Will the Mall to Base Village connection close? The Skittles gondola is scheduled to run through June and July 2027, close for construction starting in August, and reopen on Thanksgiving 2027. The Town is planning other transportation between the two during the closure.
If you own near the Mall, or are considering a unit there, and want to know where a specific building falls on this calendar, Steve Harriage is happy to go through it with you, from which projects it faces to how its value reads today. Start with a home valuation or let's connect.